Work Program Schedule
X – Tasks Completed
June 2010 – August 2010
PHASE 1: BACKGROUND ANALYSIS
- Project Initiation Meeting X
- Site Visit/Photography X
- Prepare Base Mapping X
- Assessment of Background Studies X
- Regulatory Analysis Review X
- Physical Analysis of Study Area (Opportunity + Constraints) X
- Preliminary Technical Background Report X
- Final Technical Background Report X
- Project Management Meeting X
September 2010 – December 2010
PHASE 2: NEIGHBOURHOOD MASTER PLAN & RECREASTION/SPORTS COMPLEX MASTER PLAN
- Project Management Meeting X
- Identify Neighbourhood & Site Plan Design Principles X
- Prepare Workshop Materials X
- Identify Neighbourhood & Site Plan Design Principles X
- Prepare Draft Recreational/Sport Complex Site Structure X
- 2 Day Public/Stakeholder Charrette: Neighbourhood & Recreational /Sport Complex Master Plan Design X
- Refine Workshop Outcomes X
- Prepare Preferred Neighbourhood & Recreational Structure Plan X
- Prepare Draft Urban Design + X
- Architectural Guidelines Report X
- Prepare Final Draft Neighbourhood Structure Plan + Urban Design and Architectural Guidelines Report
- Prepare Final Draft of Recreational/Sports Complex Master Plan
- Project Management Meeting
- Task Force Presentation of Neighbourhood Master Plan & Recreational/Sport Complex Master
December 2010 – March 2011
PHASE 3: FINAL MASTER PLAN + GUIDELINES REPORT
- Prepare Final Neighbourhood Master Plan
- Project Management Meeting
- Prepare Final Urban + Architectural Design Guidelines Report
- Prepare Final Recreational/Sports Master Plan + Guidelines Report
- Project Management Meeting
- Public Open House
- Presentation to Committee of the Whole + Council