Notice of Pre-Construction Public Information Centre 

For Improvements to Shellard Lane - Phase 2
(McGuiness Drive to the West City Limit)

Schedule and Description of Work

Shellard Lane Phase 2 from McGuiness Drive to the West City Limit is scheduled for reconstruction from early March to Fall 2018. This section of the road will be urbanized to match the look of Phase 1, and will include the following design features:

  • Road widening to 4 lanes with curbs, turn lanes and median islands;
  • New intersections linking proposed developments on the north and south sides of Shellard Lane;
  • New traffic signal;
  • Multi-use trails and sidewalks;
  • Storm drainage and new water mains; and
  • Illumination and landscape plantings.

Ward 1 - Shellar Lane Phase 2

Road Closure and Traffic Detour

Phase 2 will be closed to public traffic for the duration of construction. The extensive road grade changes and large culvert crossing installations, and site conditions will not allow for safe traffic movement through the construction. Detour routes will be posted in the area and along the County roads to help direct traffic to and from the neighbourhood.

Related Documents

PDF download icon graphic The documents below require the Adobe Acrobat Reader. Click to download the Acrobat Reader plugin to your browser.

Clicking on any of the documents below will open a new browser window.

Notice of Pre-Construction Public Information Centre - Rescheduled for March 22, 2018 (PDF)

Notice of Pre-Construction Public Information Centre - February 8, 2018 (PDF)

Ward 1 Public Meeting Transportation Initiatives and Winter Service Update PowerPoint Presentation (PDF)

Mount Pleasant Street / Clench Avenue / Beckett Drive Intersection (PDF)