Road Construction Update 

For Immediate Release
4/5/2012 
Contact: City of Brantford 
Phone: 519-759-4150 

The City of Brantford will be carrying out construction on the following streets as noted below. Please note that traffic and pedestrians may be inconvenienced during construction activities and these closures.  Months noted are anticipated periods of construction.

April 2012 – June 2012

Location:  Leonard Street (Wilkes Street/Burwell Street)
Scheduled Work:  Road, Sewer and Watermain Construction

Location:  Main Street (Buffalo Street/Terrace Hill Street)
Scheduled Work:  Road, Sewer and Watermain Construction

Location:  Murray Street (Alice Street/Grey Street)
Scheduled Work:  Road, Sewer and Watermain Construction

May 2012 – June 2012

Location:  Grey Street (Clarence Street/CN Tracks)
Scheduled Work:  Road, Sewer and Watermain Construction 

Location:  Brooklyn Avenue (Mt. Pleasant Street/220m East)
Scheduled Work:  Water Quality Watermain Improvements 

Location:  Park Road North (Dunsdon Street/#655 Park Road North; Elgin Street (General Street/200m West)
Scheduled Work:   Sidewalk Construction

May 2012 – July 2012

Location:  William Street (Waterloo Street/West Street)
Scheduled Work:  Road, Sewer and Watermain Construction

Location:  Gilkison Street (Elliott Street/Mt. Pleasant)
Scheduled Work:  Multi-Use Trail

Location:  Forest Road (Colborne Street/Hickery Place)
Scheduled Work:  Road and Watermain Construction

May 2012 – September 2012

Scheduled Work:  Road Restoration and Resurfacing 

  • Adelaide Avenue (Brisbane/40m East of Townsville)
  • Brisbane Boulevard (Linden/Grey)
  • Canberra Court (Complete)
  • Clarence Street (Colborne/Nelson)
  • Coachwood Road (Dunsdon/Brier Park)
  • Garden Avenue (Elgin/#180 Garden)
  • Henry Street (Earl/160m West Of Stanley)
  • Hillcrest Avenue (Shellard/Bell)
  • King's Hill Lane (Hillcrest/North End)
  • Melbourne Crescent (Complete)
  • Mitchell Court (Complete)
  • Sandy Row (Strawberry/Hillcrest)
  • Sprucehill Drive (Coachwood/Winding Way)
  • Strawberry Lane (King's Hill/Hillcrest)
  • The Strand Avenue (St. George/Queensway)
  • Townsville Court (Complete)

June 2012 – July 2012

Location:  Various Streets
Scheduled Work:  Crackfilling

June 2012 – October 2012

Location:  Brantwood Park Road (Powerline Road to Dunsdon Street)
Scheduled Work:  Road Resurfacing and Watermain Construction

Location:  Clench Avenue (Mt. Pleasant Street/Gilkison Street)
Scheduled Work:  Road and Watermain Construction

Location:  Dorothy Street (Erie Avenue to Lida Street)
Scheduled Work:  Road, Sewer and Watermain Construction 

Location:  Arthur Street (Murray Street/Rawdon Street)
Scheduled Work:  Road, Sewer and Watermain Construction

Location:  Lansdowne Avenue (Devonshire Street/Morrell Street); Devonshire Avenue (Burwell Street/Lincoln Avenue)
Scheduled Work:  Road, Sewer and Watermain Construction

Location:  Cumberland Avenue (Rowanwood Avenue/End); Hampton Street (Rowanwood Avenue/End)
Scheduled Work:  Water Quality Watermain Improvements

Location:  Greenwich Street Trunk Sewer
Scheduled Work:  Sewer and Watermain Construction